The client
The client is a large energy company headquartered in Abu Dhabi, with critical assets spread across remote field sites and a central maintenance function.
At every wellsite, a set of safety-critical equipment stands between a fault and an incident: firewater pumps, emergency shutdown valves, gas detection heads and deluge systems. They rarely operate, so the only proof they will work is regular, recorded testing.
The challenge
Test schedules for safety-critical equipment lived in spreadsheets, and evidence came back on paper, if at all. Visits to remote sites were planned one task at a time.
- Service dates for safety-critical items were missed without warning.
- Overdue tests were postponed informally, with no record of who agreed.
- Defects found during tests reached the planners late.
- There was no reliable view of compliance by site for management or auditors.
What they set up in Asset Infinity
The company registered each wellsite’s safety-critical equipment in Asset Infinity and attached a preventive plan to each item, with test results recorded on the mobile app.
A plan for every safety-critical item
Fire pumps, shutdown valves and gas detectors each carry a dated test plan that raises the work order when due. (Maintenance)
One trip, all tasks due
Work orders due at the same wellsite are assigned together to the visiting crew, so a long drive covers everything that site needs. (Work)
Proof in the checklist
Test checklists require readings such as valve closure time and detector response, plus photos and a signature, before the task can close. (Maintenance)
Deferrals need approval
A test that cannot be done on time goes through an approval step, so every postponement has a reason and an approver on record. (Platform)
How it works day to day
A round of safety-critical testing at a wellsite now goes like this.
- Maintenance planner: reviews what falls due. The planner sees every test due at each wellsite over the coming weeks, raised by the preventive plans.
- Maintenance planner: builds the site visit. All tasks due at one wellsite are assigned to the same crew for the same trip, with checklists attached.
- Field storekeeper: issues the parts. Seals, filters and detector heads needed for the visit are issued from the field store to the work orders.
- Instrument technician: tests and records. On site, the technician scans each item, carries out the test and enters readings, photos and a signature on the mobile app.
- System: turns a failure into work. A failed test raises corrective work for that valve or detector, so the defect is tracked to closure.
- Field superintendent: approves any deferral. If a test cannot be done, the request to defer it comes to the superintendent with a reason and is approved or refused on record.
- Asset integrity manager: reports compliance. Dashboards show completed, overdue and deferred tests by site and equipment class for management and auditors.
Before and after
| Before | With Asset Infinity | |
|---|---|---|
| Test schedules | Spreadsheets, often missed | A preventive plan on every item |
| Site visits | One task per trip | All tasks due at a site in one visit |
| Evidence | Paper, if returned | Readings, photos and signatures on the record |
| Postponements | Agreed informally | Approved with a reason, on record |
| Defects | Reached planners late | Raised as corrective work at once |
| Compliance view | Unreliable | By site and equipment class |
How it rolled out
- Practices and history. Existing maintenance practices were reviewed, and legacy service records moved onto each item of equipment.
- Schedules configured. Maintenance categories, schedule rules and site-wise workflows were set up for each service function.
- Field crews trained. Maintenance and operations teams had hands-on sessions, followed by a support plan with regular reviews.
The results
- 40% better maintenance compliance
- Safety-critical tests completed on schedule across field sites
- Evidence for every test held on the equipment record
- Every postponement approved and recorded
- Fewer unplanned service gaps and delays
- Better continuity in the field through timely maintenance
Why it worked
Evidence, not ticks
Required readings mean a test cannot be closed without the numbers that prove it was done.
Remote sites, fewer trips
Grouping due work by wellsite makes each long drive count.
No silent postponements
The approval step turns a quiet slip into a visible decision with someone accountable for it.
Looking ahead
With every safety-critical item on a plan and every test backed by recorded evidence, the company can show at any time which wellsites are fully tested and which need attention.
The test history now on each item also shows which equipment fails its tests most often, information the reliability team can use to decide what to replace or test more often.