Preventive Maintenance, Inspections & Shutdowns
The planned work that keeps equipment running, the inspections that prove it was done, and the analysis that tells you what to fix for good. This walkthrough covers planned maintenance in Asset Infinity: preventive plans, the forward schedule, capacity, inspections, shutdowns, reliability and root cause analysis. It’s shown on a demo manufacturer with plants in Columbus and Greenville.
What you’ll see:
- Maintenance plans triggered by the calendar, by meter readings like running hours, or by condition, such as vibration over a limit
- Task lists built from reusable blocks, with mandatory steps, photos and limits
- Meter readings from the mobile app and from sensors that raise work by themselves
- Maintenance Due: raise early, defer or skip each round with a reason, in a list or a calendar
- Capacity planning that weighs scheduled work against the roster, day by day, and a 52-week forecast
- Digital inspection rounds with limits and critical checks, where failures raise corrective work orders automatically
- Shutdown planning: readiness, the work package, the critical path, windows and milestones
- Reliability: availability, MTBF, MTTR, recommendations and the worst performers in the fleet
- Five whys root cause analysis with evidence, plus corrective and preventive actions that are checked to see if they worked
Asset Infinity is one platform for your assets, the maintenance that keeps them running, the stores and suppliers behind them, and the IT devices on your network.
Book a demo or start your 14-day free trial at https://www.assetinfinity.com, email sales@assetinfinity.com, or call +1-855-823-2600.
Transcript
Introduction
This is the Maintenance module in Asset Infinity: the planned work that keeps equipment running, the inspections that prove it, and the analysis that tells you what to fix for good. Preventive plans, the forward schedule, capacity, inspections, shutdowns, reliability and root cause analysis. We'll walk through it on Northwind, a manufacturer with plants in Columbus and Greenville. Planning sits under Work in the main menu: Maintenance Due, Capacity, Shutdowns, Plans and Inspections. Reliability and Root Cause sit under Assets, beside the equipment they're about.
Part 1: Maintenance plans
A maintenance plan is a rule: what to do, when, and what it needs. Northwind has five. A weekly lubrication round covers every centrifugal pump by category. A quarterly overhaul fires every quarter, or every two thousand running hours, whichever comes first. A statutory fire pump check raises an inspection instead of a work order. And a predictive plan fires when vibration on pump P-102 passes seven point one millimeters per second. Inside a plan: what it is, and when it fires. The schedule holds both triggers, the meter and the calendar. Tasks are built from reusable blocks: isolate and lock off, then a quarterly pump service, then a step that's specific to Columbus. A step can be mandatory, demand a photo, or carry a limit, like bearing vibration between zero and seven point one. Parts, tools and skills tell the readiness check what to look for before a round is raised. Meter and condition triggers read the asset itself. P-102's running hours are logged from the mobile app, and its vibration streams in from a sensor every hour. When a reading crosses the limit, the predictive plan raises its round by itself, and only once, however long the reading stays high.
Part 2: Scheduling and capacity
Maintenance Due is the forward view of every round: its plan, the asset, where it is, when it's due, and whether work has been raised. Raise one early, defer it to a new date, or skip it, each with a reason. Plans that raise their own work do it on time, like this monthly pump round, already a work order. And the calendar shows the month at a glance. Capacity planning weighs the work scheduled against the hours your team is rostered, day by day. October has seventy-two hours of work against six hundred rostered, but one day is over: Saturday the seventeenth, the cooling water shutdown, at a hundred and fifty-one percent. Open a day to see what wants it, what's in the way, and who's on. By technician lays every job out on each person's roster. And the fifty-two week view forecasts the year ahead from every plan: two hundred and eighty jobs and rounds, and the heaviest week, so you can hire, contract or move work before it becomes a problem.
Part 3: Inspections
Inspections are digital checklists, carried out as rounds. Northwind has two: a pump condition survey that passed with observations, and the weekly statutory fire pump inspection, which failed critically. Each check can be mandatory, expect a photograph, and carry a limit. Discharge pressure at churn should read eight to twelve bar. It read five point four. That check is critical, so its failure fails the whole round. Once submitted, the answers are frozen. And each failure became a finding that raised its own corrective work order, automatically, at the severity it deserved.
Part 4: Shutdowns
Shutdowns and turnarounds are planned as one package. This Saturday shutdown takes the cooling water pump hall offline for sixteen hours. Readiness shows what's missing, by kind: a permit not yet issued, a tool still to arrive, and fitters still to be named. Two jobs can't start until something arrives. The work package holds five jobs, and what each one waits on. The critical path chains them: the bearing, then the alignment, then the quarterly check. That's eighteen hours of work in a sixteen-hour window, and the screen says so before the plant stops, while there's still time to cut scope or add a crew. Milestones track the gates, like the torque wrench that still has to arrive.
Part 5: Reliability and root cause
Reliability turns history into numbers: availability, mean time between failures, mean time to repair, and hours down. Then it says what to do about it. A drive-end bearing that has failed ten times the same way: worth a root-cause investigation. A pump that has cost a hundred and twenty percent of its price to maintain: worth costing a replacement. And the worst performers, ranked against the rest of the fleet. Root cause analysis runs as five whys, and every answer needs evidence. The pump stopped because the bearing seized. It seized because it was running hot. It ran hot because the shaft is misaligned. And it's misaligned because the baseplate grout has degraded. That's the root cause. Actions follow the cause. The corrective one, realigning the pump, was done and verified, but the review found it didn't work: vibration was back within five weeks. So the preventive action is the one that matters: re-grout the baseplate at the next shutdown, and add a quarterly alignment check to the plan. And the investigation can't be concluded until a finding is marked as the root cause. That's the Maintenance module in Asset Infinity: plans that fire on time, rounds that prove it, shutdowns that fit, and failures that don't come back. Schedule a demo, or start your free trial today.