The client
The client is a solar EPC (engineering, procurement and construction) company building large rooftop and ground-mounted plants for industrial, commercial and utility customers.
Every project runs through installation, wiring, inverter setup, testing, quality checks and commissioning before the plant is handed over. Subcontractors, the EPC’s own engineers and field teams all work on the same site, and the client accepts the plant only when every record is complete.
The challenge
Installation records decide whether a client accepts a plant, and they were kept on paper by many hands. When a record was missing, someone had to go back to site to find out what had been done.
- Commissioning logs were filled in differently by each team.
- Cable tests, inverter settings, safety checks and module inspections went missing.
- Spares, consumables and materials used on site were tracked in pieces.
- Nobody could say for sure who installed what, and when.
- Missing checklists and test results meant repeat site visits and delayed handovers.
What they set up in Asset Infinity
The EPC ran its site work in Asset Infinity, with technicians filling in checklists in the mobile app and supervisors approving from anywhere.
Tasks for each team
Work is assigned to a named contractor or in-house team, and project managers see what is done, pending and late, day by day. (Work)
Commissioning checklists and test records
Installation, wiring, inverter and safety checks are mobile checklists with required fields, photos and signatures; IR, open-circuit voltage, torque and earthing results are time-stamped and approved remotely. (Maintenance)
Materials on site
Cables, junction boxes, inverters, mounting hardware, fuses and connectors are issued against the job, with low-stock alerts before peak work. (Stores)
A record for every installed asset
Each inverter and string is in the register with its test results, photos and documents, and these come out as reports for the handover pack. (Assets)
How it works day to day
A typical day on site now runs through the mobile app, with the office watching the same records as they come in.
- Project manager: plans the day’s work. Each task (string wiring, an inverter, a section of modules) is a work order assigned to a named contractor or in-house team, with its checklist attached.
- Field technician: fills in the checklist on the phone. Required fields cannot be skipped. The technician enters readings, takes photos and signs off each step where the work was done.
- Field technician: records the tests. Insulation resistance, open-circuit voltage, torque and earthing results go in against the asset they belong to, time-stamped as they are entered.
- System: turns a failed check into work. A check that fails can raise a corrective work order for the team responsible, so a fault found in testing is fixed before handover.
- Storekeeper: issues materials against the job. Cables, junction boxes, connectors and fuses are issued to the work order, so the record shows what was used and by which team. Reorder advice flags items running low.
- Supervisor: reviews and approves remotely. Completed checklists and test results arrive for approval from anywhere, so a site visit is needed only when something looks wrong.
- Project manager: builds the handover pack. Checklists, test results, photos and documents for the site are pulled into reports for the client’s acceptance.
Before and after
| Before | With Asset Infinity | |
|---|---|---|
| Commissioning logs | Paper, filled in differently by each team | Mobile checklists with required fields and signatures |
| Test results | Cable and inverter tests often missing | Time-stamped results against each asset |
| Materials | Tracked in pieces across sites | Issued against each job, with low-stock alerts |
| Accountability | Unclear who installed what, and when | Every task tied to a team, a date and a sign-off |
| Approvals | Supervisor on site to check work | Reviewed and approved remotely |
| Handover | Chasing paperwork, repeat site visits | Complete records, zero missing documents |
How it rolled out
- Standards kept. Existing technical testing standards stayed the same; only the paperwork moved to the app.
- Field teams trained. Engineers and contractors were trained on the mobile checklists.
- Rolled out by project type. Rooftop and utility-scale projects in several states moved to the new way of working.
The results
- 100+ hours saved per site on documentation and rework
- 0 missing documents at client handover
- 40% fewer supervisor site visits
- Faster commissioning through standard checklists and real-time approvals
- Less material wastage and clear accountability for what was used
- A digital archive for audits, maintenance and warranty claims
Why it worked
Standards did not change
The EPC kept its existing technical tests. Only the paper moved to the app, so teams had nothing new to learn about the work itself.
Records made at the source
Readings and photos are entered where the work is done, by the person who did it, so there is nothing to copy up later.
One record per asset
Each inverter and string keeps its own history, which serves the handover, later audits and warranty claims alike.
Looking ahead
By moving commissioning logs, test results, materials and handover records into one system, the EPC closes projects faster and hands clients a complete record of what was built.
The same asset records carry on once a plant is running: preventive maintenance plans, inspections and warranty claims all start from the history built during construction.